2 days left — Registration closes 2026-10-31.
CLATcoach · Current Affairs
Legal Updates
Judgments · Amendments · Notifications
Judgment

Bombay High Court: Section 9 of the Arbitration Act protects a claim to specific performance, not just the land

Bombay High Court1 min readPublished
Illustration: Bombay High Court

The Bombay High Court has set aside a single judge's refusal to grant interim protection under Section 9 of the Arbitration and Conciliation Act, 1996, to a group of doctors who had invested Rs. 60 lakh in 2005 under a Memorandum of Understanding with a builder and others for commercial premises to be constructed on a plot in Goregaon, Mumbai. The builder neither returned the money nor delivered the promised premises, and was negotiating to transfer development rights in the land to a third party. A Division Bench of Justices A. S. Gadkari and Kamal Khata held that interim protection under Section 9 exists to preserve the subject matter of a dispute pending arbitration, and that although the appellants had no direct right over the land itself, they were entitled to the commercial premises to be built on it; letting the respondents create third-party rights in the land would frustrate their claim for specific performance and leave them only a claim for damages.

The Bench found the respondents' conduct — using the appellants' money interest-free for over 21 years while claiming the agreement had lapsed — prima facie showed an intention to cheat within the meaning of Section 420 of the Indian Penal Code. It allowed the appeal and restrained the respondents from creating third-party rights in the land. As a Bombay High Court ruling, this binds courts in Maharashtra and Goa; it is not a Supreme Court precedent.

Quick check
Under Section 9 of the Arbitration and Conciliation Act, 1996, why did the Bombay High Court restrain the respondents from creating third-party rights in the disputed land?
  1. To give the appellants direct ownership rights over the land itself
  2. To preserve the subject matter of the dispute so the appellants' claim for specific performance was not frustrated
  3. Because the land had already been declared government property
  4. Because the respondents had been convicted of cheating
Show the answer ↓

Answer: B. The Court held that Section 9 protects the subject matter of a pending arbitration, and that allowing third-party rights to be created would leave the appellants with only a claim for damages instead of specific performance.

Source document

Issued by Bombay High Court. If this summary and the source differ, the source is right — tell us and we will correct it.

Revising the month? All 178 legal updates from October 2026 →