Supreme Court quashes land acquisition for Odisha mining project over missing 80% consent

Supreme Court of India1 min readPublished
Illustration: Supreme Court of India

The Supreme Court set aside a land acquisition in Sundergarh district, Odisha, carried out for a private mining company's surface rights, holding that the State had failed to comply with the mandatory consent safeguard under Section 2(2)(b) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. In Bibol Toppo v. State of Odisha, villagers from Kukuda, Bihabandha and Lanjiberna had challenged the acquisition of their land for Dalmia Cement Bharat Ltd.'s mining operations, after the Orissa High Court dismissed their writ petition. Justices Dipankar Datta and Satish Chandra Sharma held that where land is acquired by the government for a private company for a public purpose, the proviso to Section 2(2)(b) requires prior consent of at least 80 percent of the affected families, obtained as part of the Social Impact Assessment study mandated by Section 4, before the acquisition proceeds; the State had not shown such consent was validly obtained at the prescribed stage.

The Court also held that the State could not deny an appellant's locus standi for a curable defect, such as a missing signature on an affidavit, after itself failing to keep land records updated during the acquisition process; a Constitutional Court should not reject a claim on technical grounds traceable to the State's own default. The acquisition, and all notifications issued pursuant to it, were set aside, though the State remains free to initiate a fresh, compliant acquisition.

Quick check
Under the proviso to Section 2(2)(b) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, land acquired by the government for a private company for a public purpose requires:
  1. No consent, since the government is the acquiring authority
  2. Consent of only the families residing within the mining lease area
  3. Prior consent of at least 80% of the affected families, obtained along with the Social Impact Assessment
  4. Consent of the Gram Sabha alone, irrespective of individual families
Show the answer ↓

Answer: C. The Act requires 80% consent of affected families for private-company acquisitions, obtained alongside the Social Impact Assessment study; consent of the Gram Sabha alone, or of lease-area residents alone, cannot substitute for this, and it is not dispensed with merely because government is the acquiring authority.