Bombay High Court orders MSEDCL to refund telecom tower operators wrongly billed under its own circular
Indus Towers and other telecom infrastructure companies had challenged Maharashtra State Electricity Distribution Company Limited's (MSEDCL) continued levy of 'Commercial' tariff on their mobile towers between March and September 2010, even though MSEDCL's own circular dated 20 April 2010 had restored the lower 'Industrial' tariff with effect from 20 March 2010, subject only to the operators furnishing an undertaking. The petitioners said this delay in implementation cost them about Rs 60 crore in excess payments that MSEDCL never refunded despite repeated demands. MSEDCL argued the writ petition, pending since 2013, should be dismissed because the petitioners had an efficacious alternate remedy under the Electricity Act, 2003 (the grievance redressal forum and the Electricity Ombudsman), and that telecom towers were not an 'industrial' activity.
The Division Bench of Justices Suman Shyam and Gautam A. Ankhad held that the requirement to exhaust an alternate statutory remedy is a rule of discretion, not an inflexible bar to Article 226 jurisdiction, and it would be unfair to relegate the petitioners elsewhere after thirteen years. On merits, since MSEDCL never denied issuing the circular, it was bound, as a State instrumentality, to act consistently with its own directions; charging Commercial tariff contrary to it was arbitrary, amounted to unjust enrichment, and violated Article 14. The Court issued a mandamus directing refund of the differential amount within 60 days, with 9% annual interest if delayed.
Quick checkWhy did the Bombay High Court reject MSEDCL's objection that Indus Towers should have pursued remedies under the Electricity Act, 2003 instead of filing a writ petition?- Because the Electricity Act, 2003 does not apply to electricity distribution companies
- Because writ jurisdiction under Article 226 can never be excluded by statute
- Because the petition had remained pending for over a decade, and the rule requiring exhaustion of an alternate statutory remedy is a rule of discretion, not an inflexible bar to Article 226 jurisdiction
- Because MSEDCL had consented to the petitioners bypassing the statutory remedy
Show the answer ↓
Answer: C. The Court held that exhaustion of alternate remedies is a self-imposed rule of discretion, and relegating the petitioners after thirteen years' pendency would have been unfair, so it entertained the writ instead of insisting on the Electricity Act's grievance mechanism.
Issued by Bombay High Court. If this summary and the source differ, the source is right — tell us and we will correct it.