36 days left — Registration closes 2026-10-31.
ProgrammesCruciblePricingScholarshipLegal UpdatesBlogDiagnostic TestApplyStudent Login
CLATcoach · Current Affairs
Legal Updates
Judgments · Amendments · Notifications
Judgment

Supreme Court: a clause barring interest on 'delayed payments' can also bar pre-reference interest

Supreme Court of India1 min read

In a dispute traced back to a 1996 public-works contract for a Gas Turbine Power Project in Tripura, the Supreme Court examined whether an Arbitral Tribunal was competent, under Section 31(7)(a) of the Arbitration and Conciliation Act, 1996, to award pre-reference interest despite a contract clause restricting interest. The Arbitral Tribunal had awarded the contractor Rs. 3.30 crore along with pre-reference interest; the Commercial Court disallowed the interest, citing Clause 54 of the contract's General Conditions, but the High Court restored it, treating Clause 54 as identical to the clause construed in State of U.P. v. Harish Chandra and Co., a case decided under the since-repealed Arbitration Act, 1940, which had been held not to bar pre-award interest.

The Supreme Court disagreed, holding that Clause 54 contains an additional line specifically barring interest on delayed payments, over and above money withheld due to a dispute, and that this wording brings it within the later line of decisions beginning with Sayeed Ahmed & Company v. State of U.P., which treat such clauses as a complete bar on an arbitrator's power to award interest for both the pre-reference and pendente lite periods. The Court held the appellant had not waived the point, having raised it before the Tribunal itself, and set aside the grant of pre-reference interest as being in excess of the Tribunal's jurisdiction.

Quick check
Under Section 31(7)(a) of the Arbitration and Conciliation Act, 1996, an Arbitral Tribunal's power to award pre-reference interest is:
  1. absolute and cannot be restricted by the contract
  2. subject to any agreement between the parties otherwise providing
  3. available only if both parties consent during the arbitration
  4. limited to disputes referred after 2016
Show the answer ↓

Answer: B. Section 31(7)(a) allows the tribunal to award interest 'unless otherwise agreed by the parties', so a contract clause validly barring interest displaces the tribunal's default power.

Source document

Issued by Supreme Court of India. If this summary and the source differ, the source is right — tell us and we will correct it.